1.1 Prerequisites and main ideas

The framework functionality requirements are formed as a result of the requirements analysis for various purposes of ICS functioning, their development problems, commissioning and operation. Among these are following:

  1. integration problems with MES/MOM and other subsystems;
  2. low object observability, even with a sufficient amount of measurement data;
  3. “static” process diagnostics without reference to the type of product and the specificity of the conditions (Batch-processes for example);
  4. poor implementation of self-diagnosis and neglegense of failures in the ICS system itself ;
  5. insufficiently thought-out mechanism for alarms and events functioning;
  6. complexity, significant time spent on debugging the system;
  7. complexity, significant time spent to identify the fact of failure and eliminate the causes;
  8. complexity, significant cost of resources for staff training;
  9. complexity, significant time spent on software development

These problems and ideas for solving them are discussed below in more detail .

Integration with MES/MOM and other subsystems

Problems of integration with MES/MOM level applications and other subsystems are primarily not in the scope of communication exchange (these problems are solved at a time, for example, by using standard protocols, OPC, EDDL, FDT/DTM, FDI, etc.) but in functional representation of lower level entities (objects) for upper level and coordination on one level. Many existing solutions transmit “raw” data to the top level of the SCADA/HMI, which must first be processed. Due to the lack of information (such as data not displayed) and the relatively low exchange rate between PLCs and SCADA/HMI, some important KPIs (Key performance indicators) and statistics or aggregate data at level 2 required by the 3rd (MES/MOM) are difficult to calculate, or their value cannot be provided with a given accuracy.

An additional problem is the lack (usually) of information about the data reliability. For example, the failure of the PLC channel is ignored and displaed on SCADA/HMI and transmitted inadequate data to the upper MES/MOM levels.

At the same time, the computing resources of controller devices, including industrial controllers, have grown significantly. Therefore, data pre-processing should be done directly in the level of control devices for the process or machine (and even on the field level). The concept proposes to use the ideas and model of the equipment hierarchy from the standards ISA-88/95/106 and RAMI4.0 (German reference model Industry 4.0), according to which, an information on each equipment is represented by its set of structures in the control device that runs this equipment. This makes it possible to make calculations based on the measurements and control location by sertain equipment and also makes the system more flexible in terms of functional distribution options. The principle of functional distribution (IEC TR 62390) is used, which provides for the division of the entire Application into functional blocks and can be used in different management paradigms (centralized or decentralized IEC 61131 and distributed IEC 61499). An example of such an approach is the use of structures and functions used for motor control directly in the control systems of electric drives (PDS, frequency converters) for profiles CiA402, ProfiDrive, etc.

It is necessary to support the ideas underlying the above integration standards at the level of software and hardware at the level of PLCs and below to implement them. As practice shows, the SCADA/HMI support of the specified in the standards functionality is specific and very different. This leads to the fact that most of the functionality has to be implemented independently, which is easiest and most flexible to do in the programmable controller, if you use the paradigm of IEC 61131 or hybrid.

Observation of the object (situational awareness)

Current research in the field of creation and operation of human-machine interfaces in ICS has shown the need to create a context for better situational awareness. In other words, the display of a numerical value is often not accompanied by its context (location within the norm, comparison with the average, etc.), which poorly affects the situational awareness.

Contextual monitoring requires the use of structured rather than “flat” variables that contain all the necessary information about the process variable anywhere. For example - this is the state of the process parameter (the presence of different level alarms, the value reliability, the state of service, etc.), the norm, minimum/maximum value, etc. The context can be used both on HMI devices, and in PLC program functions.

At the same time, there are a large number of unused device resources throughout the system. The rapid introduction of frequency converters and other intelligent devices in ICS combined with the total spread of industrial networks (field buses) makes it possible to obtain a large amount of additional data on the process state without additional cost. This makes it possible to analyze the process at a higher level.

For example, you can get real-time information from the frequency converter about current power, torque, voltage and current consumption,calculate a KPI that can be used to evaluate its performance. Minor faults usually do not occur during operation, but increase energy consumption and, ultimately, still lead to abnormal stops. KPI Calculation and its comparison with norm gives the chance to pay attention to malfunction even before an emergency stop.

It is possible to increase situational awareness by comparison with the reference model. For example, the balance of the level in a tank and in/out flow, or a comparison of pressure with the pressure characteristic of the pump at the specified speed. By integrating the control device with cloud services, the context can be formed on the basis of cloud computing, and those in turn can use the existing context of the variable.

The above possibilities can be relatively easy implemented using the principles of object-oriented programming and the development of a general flexible concept.

Alarm Management for process and equipments, troubleshooting

Alarm subsystem

The problems of badly developed alarm subsystem and ways to deal with it are well described in ANSI/ISA-18.2. In particular, the most typical are alarm flooding caused by faulty equipment or incorrect settings of the alarm subsystem. The implementation of the alarm subsystem functions strongly depends on the capabilities of SCADA/HMI. Thus, a typical unused feature of the SCADA/HMI package (or no such feature at all) is the temporary removal of a service alarm. This often leads to the leveling of the alarm subsystem functions in general. The possibility of decommissioning the channel would greatly simplify system maintenance, as a faulty channel would not lead to alarm handling. In addition, the fact of the channel decommissioning can be processed in other parts of the program, such as processing control valve with a limit switch, which is temporarily decommissioned.

An additional problem is the coordination of the SCADA/HMI alarm subsystem and the control of light and sound alarms. Due to the high dependence of the alarm subsystem implementation on the capabilities of SCADA/HMI, it makes sense to bring most of the alarm processing functions to the controller level, which usually has more possibility to implement algorithms. An additional argument to this is the need to use a locking functions at the PLC level and to define an additional state of control logic behavior.

For periodic multi-recipe production, the equipment is idle between production periods and the requirements for the process change depending on the recipe. That is a classical approach to ICS of continuous processes, in which the formation of settings for process alarms is carried out during software development (and even in the process of configuration) is not suitable for this case. For example, the temperature of the heat exchanger outlet should be monitored only during the heating/cooling process of the product (not during standstill or washing), and the emergency and warning values depend on the type of product. To solve this problem, the alarm subsystem must adapt to the requirements depending on the type of product, equipment condition and process, which in most cases is easier to do at the controller level than SCADA/HMI. Given that the ISA-88 standard has been developed and repeatedly tested for the management of periodic production, it makes sense to be based on its bases.

Diagnosing equipment

“Flat” (unstructured) space of variables, which were used in PLCs in the 20th century, is often the basis for software to this day, although modern tools allow the use of object-oriented programming elements. “Flat” variables contain only the values of the process parameter, but for proper process control it is necessary to have its full context. As mentioned above, a very important property of the process variable is the reliability of the data, which is determined by a number of indicators, among which is the failure of the channel. Modern PLCs provides a lot of software diagnostics, however, significant costs (not provided at the beginning of the life cycle) to write a program for additional reliability processing in control functions in most cases lead to neglect of these capabilities and lack of software diagnostics at all. This does not apply to ICS for functionally hazardous processes.

Reliability can be displayed in the status of each channel and the variable associated with that channel. By passing the authenticity status together with the value to all parts of the ICS, in addition to the process states, you can enter the state of “inaccuracy” (for example, channel failure), in which you can specify a separate processing logic. This is fully consistent with all modern implementations of the state machine in process automation devices. It should be noted that the processing of inaccuracies is carried out in the same software blocks where the process variable is processed. For example, if you use the function of stabilizing the temperature control at the outlet of the heat exchanger, then if the channel fails, its value may go to the extreme position, or (worse) remain unchanged. If the inaccuracy property is present, a separate alarm will be generated for this parameter (eg “Heat exchanger temperature measurement channel failure”) and the stabilization function will move the valves to a safe state. It should be noted that such a program structure requires a state-oriented approach even for controller functions.

Troubleshooting

Lack of contextual process, equipment and control system diagnostics leads to a significant amount of time to identify the fact and cause of the fault. For example, an criticaly low alarm may occur when the input analog channel has wire break. In this case, basic software analysis could result in the channel being unreliable. It should be noted that this level is often present in modern ICS. However, a fault in the channel can be caused by a number of reasons: for example, a fault in the measuring channel to the PLC, or a fault in the electronics of the channel in the PLC itself. Modern PLCs provide the ability to deep software diagnostics of channels, identifying the causes of failure. This additional information allows you to troubleshoot much faster.

Another problem is the elimination of defective PLC parts and the replacement of devices with some characteristics to others. The presence of PLC spare modules in the enterprise is usually available only for the most critical positions. In other words, it is sometimes necessary to wait for a new module for several months to troubleshoot, which is not acceptable for all processes. Given that often the channels (or groups of channels) fail but not the whole module, and the PLC has available free (unused) channels of the same type, it would be appropriate to provide the ability to “switch channels”. Changing the device often requires a change in the measuring range, which must also be provided in the ICS.

Debugging the system

When setting up the system there are a number of difficulties associated with the implementation of ICS. Debugging the program and the system as a whole need to ensure compliance with the following requirements:

1) the need to change the state of the input variable, regardless of the value of the physical channel to test the algorithm;

2) the need for rapid response of simulated sensor signals when checking the operation of the algorithm without the existing process (for example, the sensors of the end position of the valves, when opening them);

3) the need to change the value of the output channel, regardless of the state of the program when checking the output channels.

To fulfill the first 2 requirements of the classical approach to debugging the program (step-by-step verification of the actions in the table, etc.) requires a large amount of routine work that is performed constantly. In the world of computer programming, software tests are used for this purpose, but in ICS these mechanisms are insufficiently developed. The third requirement includes the participation of the PLC software developer to perform forcing operations, change the value of the unused channel, and so on. Software simulation and forcing, which should be available from the HMI, can help with this.

Staff training

Often no attention is paid to staff training at all. The problem is related to the need to train staff directly on the real object. However, most situations cannot be simulated manually, as they depend entirely on the actual process. It is not allowed to simulate critical situations on a real object at all.

An option to overcome these limitations is to use simulation directly in the controller program, which will also make it easier to debug the software part of the system without an existing object. In addition, software packages for software development of controllers of high and medium complexity usually include PLC simulators, which allows you to “deploy” the control system anywhere.

Creating large projects

Creating large projects requires a lot of routine work. It becomes even more complicated when the software development process is performed in parallel with the design processes, which leads to constant changes in the source data for the software. As a result, the program needs to be constantly changed in several places, which leads to errors related to the human factor.

The selection of duplicate parts and their rules for implementation in the application program significantly speeds up the development process and reduces the number of errors. Changing the algorithm of a typical object with such code construction leads to a change in one place.

In addition, given the iterative development process, the constant change of requirements and initial data, it is necessary to automate development processes. The first step is to standardize the representation of software objects, the second - to create software to automate the conversion of project data (list of process variables, actuators, etc.) into program code.